Aerial view of a large industrial site at dusk with the different phases side by side, from excavation to finished building

From site to SOP

Six phases, and in each one a door that closes

The months move with sector and size. The order never changes, which is why you can know in advance what is still open to you.

The short answer

The useful question is not “are we doing AI?” but “which door closes this quarter?”. The first three are usually shut by the time anyone raises the subject; the last three are almost always still open.

The sequence

What closes in each phase

Months are indicative.

Month 0–6

Site and permits

Power, water and fibre. The grid connection is fixed here for the life of the plant.

Month 4–20

Construction and services

Floor loading, structural openings, trays and conduit. Everything that would later be concrete.

Month 12–26

Automation and OT

Protocols, PLC and SCADA. And, in the purchasing specs, who owns the data each machine produces.

Month 14–28

Cybersecurity and data

NIS2 and IEC 62443 zoning, data governance, and how it sits with the AI Act and Data Act.

Month 24–32

Commissioning and validation

IQ/OQ/PQ protocols. If a model sits in the control loop, it is validated here or not at all.

Month 30+

Ramp-up and steady state

Throughput, first-pass yield and predictive maintenance. From here only the software layer moves.

In detail

The full table

To take to the committee. It is the clearest one-screen summary of the problem.

Phases of an industrial project and the decisions fixed in each one.
#PhaseWhat is closed by the end of itMonths
01Site and permitsPower, water and fibre. The grid connection is fixed here for the life of the plant.0–6
02Construction and servicesFloor loading, structural openings, trays and conduit. Everything that would later be concrete.4–20
03Automation and OTProtocols, PLC and SCADA. And, in the purchasing specs, who owns the data each machine produces.12–26
04Cybersecurity and dataNIS2 and IEC 62443 zoning, data governance, and how it sits with the AI Act and Data Act.14–28
05Commissioning and validationIQ/OQ/PQ protocols. If a model sits in the control loop, it is validated here or not at all.24–32
06Ramp-up and steady stateThroughput, first-pass yield and predictive maintenance. From here only the software layer moves.30+

Common questions

Frequently asked questions

Are the months fixed?

No. In pharma they stretch because of validation and in logistics they shrink. What does not change is the sequence: the grid connection always precedes the structure, and the structure precedes the trays.

We are in phase 4. What is left?

Quite a lot, in fact. In phase 4 you still decide network zoning, data governance and much of the software architecture. What is gone is physical: power and structure.

Can any phase be skipped?

Skipped no, brought forward yes — and that is what we propose: moving phase 3 and 4 decisions into phases 1 and 2, while they are still cheap and reversible.

Finished modern industrial plant lit up at dusk

What phase is your project in?

Tell us which and we will tell you which doors are still open.

We call you within 48 h with the decisions you are about to close

Thirty minutes with an engineer on our team. You keep a written summary, whether you hire us or not.

Free and with no commitment. A person gets back to you, not a sales rep. By submitting you accept the privacy policy.