Greenfield
You decide everything, and nearly all at once
A greenfield is the one chance to build a plant designed for AI from the first drawing. It is also where getting it wrong today is cheapest, and where finding out in month 28 is most expensive.
The short answer
On a greenfield every door is open on day one and they close in order. The grid connection is requested in month 2, the structure is signed in month 8 and the trays in month 14. By the time somebody asks “and what about AI?”, three of the five decisions are already signed.
The irreversible part
What you decide, and the document it gets signed in
These are not meetings: they are concrete deliverables with a date and a signature. This is what to look at before approving them.
-
01
Grid capacity request to the utility
Month 2. Sized against year-one process consumption. Adding headroom here costs a percentage; adding it in year five means eighteen months of paperwork.
-
02
Structural drawing and floor loading
Month 6–8. Defines where weight can go and where it cannot. A technical room not foreseen here will not fit later without reinforcement.
-
03
Services design: trays and openings
Month 10–14. The cheapest thing to leave provisioned and the most expensive to add. A run of empty tray is the best investment in the project.
-
04
Process equipment purchasing specification
Month 12–20. This is where it is decided, almost always without debate, who owns the data each machine produces and in what format it leaves.
-
05
Network architecture and OT zoning
Month 14–22. If it is not zoned to IEC 62443 now, doing it later requires a stop.
Common questions
Frequently asked questions
We are still in feasibility. Isn't it too early to talk about AI?
It is the best moment, and the cheapest. In feasibility you can still pick the site for proximity to power and fibre, which is one of the five decisions. After that you do not choose it: you inherit it.
Does this make the project more expensive?
The provisions we propose — power headroom, an empty tray, space for a technical room, a data clause in the spec — are very low cost against the total budget. The expensive option is the opposite: opening it up later.
Do you work with our engineering firm or in parallel?
With them. We do not write the design or sign drawings: we review theirs and put the questions their contract does not oblige them to ask.
What month is your greenfield in right now?
Tell us the phase and we will tell you what is still open.